Project Milestones:
2001
Hennepin/Wright cooperative agreement executed.
2001 2004
Four community meetings held.
2002
Legislation authorized demonstration project.
2002
Joint Powers Board formed.
2002
Conceptual alignment developed.
2002 2007
Preparation of official map (draft).
2004 2007
Environmental documentation.
2004 2007
Official map to be adopted by each municipality and Wright County.
2005
Congress authorizes $4 Million for TH 55 Corridor
2007 and beyond
Begin acquisition of selected right-of-way and construct safety improvement projects.
Current Priorities
Complete official mapping of the corridor
Implement access management